Contract/Lease Date: 13.05.2013 (3.7.1434 H) Lease Period: 25 years Lease Amount: SR 2,580.300 per year Land Area: 17,202 m2 Project Components: Hotel (3 stars) – Premier Inn * 121 keys (140 cells) Expected construction Duration: 18 months Expected Start of Construction: End of October 2014 Estimated Construction Budget: SR 59,620.678 Project Component Built-up Areas: Hotel 9,114.40 m2 * Commercial: 2,527.87 m2 (36 units) Total project Built-up Area: 11,908.60 m2 Progress to date: * Initial/Preliminary design completed and approved by MODON. * Initial/Preliminary design approved by Tourism Authority and waiting for official approval letter. * Design development/final design stage in Progress and expected for completion in 2015.
|
Jeddah Properties – Commercial & Hotel Project: Hotel & Commercial shops Location: Jeddah Industrial Area, KSA Client: Saudi Industrial Property Authority (Modon) |